How could the election results change expectations for data-center power use?
- After Democrats won the midterm elections on 3 November, JPMorgan expects independent power producers in places including Texas, Ohio, Pennsylvania and Georgia to face pressure. Most states have not imposed a blanket ban on data-center development, but approval hurdles for new projects are expected to rise, giving already-approved projects an advantage.
- If development slows, power prices could come under pressure; JPMorgan expects meaningful new generation capacity to come online only around 2029. This means delays to new projects could first weaken near-term power demand, rather than bringing an immediate increase in power supply.
Which parts of the power sector are likely to be affected first?
- Independent power producers and suppliers providing on-site or transitional power to data centers are more sensitive in the short term. Longer project construction timelines would first weigh on demand for bridging power; JPMorgan particularly noted a more pronounced impact on relevant suppliers in Texas and the PJM region.
- For independent power producers, the phased start of existing long-term power purchase agreements (PPAs) can add contracted revenue, providing a buffer for future revenue and balance sheets; therefore, the timing of the impact of price pressure from slower projects differs from that of the support provided by contracted revenue.
- The credit impact on regulated utilities is relatively modest. Data-center demand had supported some companies' expected earnings-per-share growth in the range of 6%–9%; if related capital spending declines, growth expectations could be adjusted, but this could also ease pressure on balance sheets from investment plans that continue to expand through 2030.
Which is stronger: corporate investment enthusiasm or obstacles to new projects?
- Company disclosures still point to strong demand from large loads: Southern Company has signed new contracts for 4 GW of large load since last quarter, bringing its total signed contracts to 21 GW. WEC increased its five-year capital plan by 10 billion dollars, mainly for generation, and set out annual compound earnings-per-share growth of 7%–9% through 2031; its debt financing plan for 2027–2031 is 18.7 billion–19.3 billion dollars. The latter points to significant financing needs behind the growth plan as well.
- Expansion in demand is also constrained by electricity affordability. U.S. residential electricity prices have risen by more than 10% since 2024, and utilities are expected to seek about 31 billion dollars in rate increases in 2026; related political pressure could lead to electricity-price freezes, lower allowed returns or closer scrutiny of capital plans.
- The scale of PJM's reserve procurement has also been revised down significantly: after utilities lowered their large-load forecasts, the revised plan is expected to procure about 630 MW, well below the original target of 6.8 GW. Although the new framework reduces service-provider risk, timely state-level cost recovery and customer guarantees remain key to preventing utilities from bearing collateral, liquidity or stranded-cost risks.
How has the credit market reflected utilities' relative performance?
- As of 4 November, utility bond spreads widened by 3 basis points in one week, less than the 4 basis points for the JULI index; year to date, utility spreads widened by 2 basis points, while JULI widened by 13 basis points. Utility spreads stood at 92 basis points, 11 basis points below JULI, indicating the sector's relatively resilient credit performance.
- This is not inconsistent with tighter project approvals: the former reflects relative movements in short-term credit spreads, while the latter could affect future demand and growth expectations. JPMorgan's view on regulated utilities also focuses on how slower capital spending could ease financing pressure; near-term pressure on power generators and bridging power suppliers is more direct.