How much of the more than 3 billion in projects is optional?
- BofA says Jereh received three letters of award from ADNOC Onshore, totaling about 2.7 billion; it also signed a project for Oman’s Al-Ghubar oil field on 21 October 2026, worth about 327 million. Recent Middle East oil and gas projects total more than 3 billion (over RMB 20 billion).
- Of the three ADNOC projects, the Ruwais Diyab gas field project is worth about 1.7 billion and includes gas-turbine sales; the Bab/North East Bab project is worth about 600 million, and the Bu Hasa project about 393 million. But nearly half the value of the latter two projects is optional; the first project also includes about 124 million of five-year operations and maintenance services, and an operations and maintenance option worth about 310 million, extendable for ten years. The nominal project value is not the same as fully secured revenue.
When will the orders turn into revenue?
- BofA expects revenue from the EPC engineering portion of the first project and the Oman project to be recognized gradually over three years starting in 2027; operations and maintenance revenue from the first project, as well as the second and third projects, will be recognized over their respective operating periods. The orders provide multi-year revenue visibility, rather than being recorded all at once upon signing.
- BofA’s model projects Jereh’s revenue to rise from RMB 18.506 billion in 2026 to 37.54 billion in 2027, while adjusted net profit rises from 2.983 billion to 6.558 billion. Both figures are brokerage forecasts, with revenue projected to nearly double; staged order recognition and growth in the gas-turbine business together support this forecast.
Why does BofA center its valuation on gas turbines?
- BofA’s view is that Jereh is shifting from an oil and gas equipment supplier to a gas-turbine integrator. Electricity demand from AI data centers, tight industry supply of gas turbines, and the company’s execution and channel advantages could drive expansion in the high-growth, high-margin gas-turbine business and offset some weakness in oil and gas.
- BofA maintains a Buy rating with a target price of RMB 168; the report lists the share price at RMB 90. Its sum-of-the-parts valuation applies a price-to-earnings multiple of 40 times forecast 2027 earnings per share to the gas-turbine business and 12 times to the non-turbine business; the lower multiple for the latter reflects a weaker outlook for global oil and gas capital expenditure. Earnings forecasts are not uniformly above consensus: BofA expects 6.40 yuan per share in 2027, below the Visible Alpha consensus of 6.54 yuan; its forecast of 8.52 yuan for 2028 is above 7.83 yuan.
What could limit the conversion of profit into cash?
- In BofA’s model, operating cash flow in 2027 is RMB 5.25 billion, below adjusted net profit of 6.558 billion; working-capital changes are negative 11.184 billion, and the cash conversion ratio is 0.8 times. In other words, even as the profit forecast grows substantially, working-capital needs keep operating cash flow below reported profit.
- Gas-turbine growth also depends on whether electricity demand from US AI data centers and tight supply persist. BofA’s downside conditions include weaker demand; delayed project approvals or an easing of supply constraints; restricted engine supply; price competition; and delays in executing Middle East projects or sanctions risks facing its business with US data-center customers.