Will Texas policy halt data-center projects?

  • Citing BNEF data, JPMorgan says Texas accounts for more than one-fifth of the U.S. data-center project pipeline, with related projects totaling more than 50 GW; changes in construction schedules could therefore affect demand for a range of power infrastructure.
  • Experts believe the separation of powers in the state government and Republicans' continued control of the Senate limit the scope for major policy changes. A more direct approach could be to tighten environmental requirements, delaying some projects by several months rather than canceling them outright. Experts expect construction to continue, but say uncertainty over project timing is greater than uncertainty over long-term infrastructure demand.

Which projects are more likely to be delayed?

  • Projects that already meet current requirements are less affected by new rules; those still far from approval face greater risk. Some projects planned for development in 2028–2029 are particularly susceptible to additional requirements or delays.
  • Developers could consider moving projects to other locations or grid regions, but power markets elsewhere in the U.S. are also tightening their requirements, so relocation cannot eliminate approval uncertainty entirely.

How can developers address the need to “get power quickly”?

  • Because the time to power is critical, developers will first procure power sources that can be obtained quickly, including less efficient, older thermal power units as transitional sources, then switch once more efficient power sources with longer delivery lead times become available. Environmental regulators may also constrain this transitional option by limiting operating hours or capacity factors for older units.
  • Experts believe gas-fired combined-cycle units are relatively likely to be accepted in Texas, while renewables alone cannot reliably meet data-center loads. Hybrid grid and behind-the-meter power supply, along with load flexibility, can help speed up power connections; smaller distributed sites may be easier to connect, but large transformers remain an equipment bottleneck.
  • 765-kilovolt transmission lines are a long-term solution, but difficulties with siting, opposition from landowners and political pressure could slow construction. The report notes that a related project was once suspended amid opposition.

Which equipment companies are better positioned, and what are the constraints?

  • JPMorgan favors companies that serve utilities and the grid more directly, reasoning that projects of this kind face a lower risk of order delays or cancellations. The report says demand for modern power infrastructure construction remains, and is positive on HD Hyundai Electric and Hyosung Heavy Industries, noting that both companies' forward P/E ratios for the coming year are in the low-to-mid teens. The report rates both Overweight.
  • However, grid-side equipment could also be affected by import restrictions: U.S. executive orders may restrict imports of transmission-grid equipment. Experts believe such restrictions are more relevant to products that connect directly to the main grid; restrictions may be less extensive if behind-the-meter equipment is adequately isolated from the grid.