How far has “six-network coordination” progressed?

  • On 6 November, the NDRC called for aligning plans, introducing supporting policies, accelerating project-database development and information sharing, strengthening funding and land safeguards and coordination of major projects, while also studying and formulating next year’s work plan. The focus has extended from coordination mechanisms to project organization and factor safeguards.
  • Earlier, on 19 August, the NDRC had studied establishing a “2+3+N” coordination mechanism for the computing-power network, new-type power grid and next-generation communications network. Ping An Securities’ power-grid team judged that “six-network coordination” is deepening toward coordination and advancement at the level of major projects.

How do coordination mechanisms translate into demand for power-grid equipment?

  • The NDRC had previously proposed including the new-type power grid in a coordination mechanism alongside the computing-power network and next-generation communications network, with State Grid and China Southern Power Grid participating in the coordination and advancement of major projects. Industry participants understand this to mean that the two major grid companies, the three major telecom operators and computing-power companies are entering a collaborative framework; this provides an organizational basis for coordinating computing-power construction with power-grid projects.
  • Ping An Securities believes computing-power infrastructure construction may bring incremental demand for grid expansion, new-type distribution and highly reliable power-supply equipment. The transmission logic is that coordination between computing-power project progress and power-grid construction would then increase demand for related power infrastructure; policy requirements for project databases, funding and land safeguards are relevant to whether demand can translate into specific construction.

Beyond incremental demand, what else is supporting power-grid construction?

  • Ping An Securities also pointed out that power-grid investment remains at a high level of activity. The continued connection of new energy, growth in electricity loads, and construction of a new-type power grid featuring coordination between the main grid, distribution grids and microgrids support the continuation of demand for upgrades to the main grid and distribution grids; ultra-high-voltage construction is also expected to continue. These are existing construction drivers beyond the incremental demand from computing power.

Which equipment companies are relevant to this investment thesis?

  • XJ Electric’s products for conventional and flexible direct-current ultra-high-voltage converter valves, as well as control and protection, have been applied on multiple ultra-high-voltage lines in China. Pinggao Electric is qualified to produce AC and DC ultra-high-voltage and ultra-high-voltage switchgear, with products covering 72.5–1100 kV. They correspond to the transmission and switchgear segments; their existing applications and product capabilities show that their businesses are connected to related construction.
  • This information reflects applications on existing lines and the scope of product coverage; it does not represent new orders resulting from the current round of coordination. The progress confirmed by the materials currently available centers on policy, project-database and factor-safeguard arrangements, while the scale of equipment demand still depends on the progress of specific projects.