How much new capacity can projects under construction support?

  • Goldman Sachs estimates total US data-center capacity at about 65 GW-gross by the end of 2026. Based only on projects under construction, additions in 2027–29 are 33/37/8 GW-gross, respectively; converted using a PUE of 1.5, this is equivalent to 22/24/5 GW-IT.
  • Compared with Goldman Sachs' own forecasts for additions of 20/24/23 GW-IT in 2027–29, capacity under construction provides a slight surplus for 2027 and exactly matches the forecast for 2028; but in 2029 it amounts to only 5 GW-IT, far below the forecast of 23 GW-IT. Thus, projects under construction more directly support forecasts for the next two years, but that support cannot be extended in the same way to 2029.

What will make up the shortfall in expansion after 2029?

  • A further 137 GW-gross of Aterio projects, planned to be added in 2027–30, are designated as “high probability,” but have not yet started construction. The classification takes into account factors including permits, financing and power supply, and does not mean that construction is already underway.
  • According to the report's charts, these announced projects correspond to additions of about 3/35/61/38 GW-gross in 2027–30; Goldman Sachs considers their execution timing riskier than that of projects under construction, and says they should be assessed project by project, particularly given the possibility of construction suspensions. Visibility into forecasts after 2029 therefore depends more heavily on whether this pipeline can advance on schedule.

Which projects could be affected by a construction pause in Texas?

  • The Texas governor-elect has called for an immediate pause on data-center construction. Texas accounts for 20% and 27% of US projects under construction and additions in 2027 and 2028, respectively; Texas, Ohio, Nevada, Georgia and Michigan together account for about 42% of under-construction and announced high-probability capacity, with Texas alone accounting for about 26%.
  • Goldman Sachs believes a construction pause does not amount to a ban on construction or project cancellations, but its reach may extend beyond projects that have actually entered main construction: Aterio counts preliminary work such as site clearing, grading and trenching as “under construction,” and such work may precede customer contracts, power-service agreements and environmental permits. Projects lacking the latter conditions could still be affected by new rules.

How could delays affect operations and suppliers?

  • Goldman Sachs lists the direct effects as delayed commissioning and higher financing costs; some projects could consequently see contracts canceled. If tax incentives are reduced, the tax burden could also rise; investments in transmission and power-generation infrastructure could also increase capital expenditure to mitigate impacts on other electricity users.
  • At the company level, IREN has the highest Texas exposure among the companies covered by Goldman Sachs, while Digital Realty and Equinix have smaller exposures to these development-focused markets. Delays in AI data-center construction could also affect server supplier Celestica and data-center Ethernet switch suppliers Celestica and Arista Networks, since the related AI infrastructure is a growth driver for them.