Why are the elections unlikely to reverse the direction of grid investment?

  • JPMorgan believes grid modernization remains a matter of bipartisan support: rising electricity consumption and interconnection requests are driving US grid upgrades, and nearly every state is also advancing legislation or regulatory measures related to grid modernization. The bank therefore expects the midterm elections to have a limited effect on necessary infrastructure investment by most regulated utilities.
  • This view supports orders for Korean high-voltage transmission equipment: JPMorgan expects most of the relevant manufacturers’ backlogs, particularly orders from regulated utilities, to remain stable.

Why can order sources cushion changes in data-center policy?

  • Currently, 80%–90% of new orders for Korean high-voltage transmission equipment manufacturers come from utilities and grid operators. Ongoing grid capital expenditures can therefore provide a layer of support for orders; this is not the same source of demand as data-center projects proceeding smoothly.
  • However, JPMorgan also notes that short-term sentiment around AI developments could weigh on valuations of related stocks, even as order backlogs remain supported by fundamentals.

What policy and cost constraints could data-center construction face?

  • Regulatory changes are more likely to appear first at the state level: local governments may adjust tax incentives, increase investment in power infrastructure, or require community benefits. Voters’ concerns about electricity prices, water use, emissions, and noise also make candidates from both parties inclined to support new regulatory guardrails. JPMorgan’s global strategy team believes that a comprehensive federal AI regulation bill is unlikely to pass in the near term, making the policy environment more fragmented across states.
  • Hyperscale cloud providers have said they are willing to contribute funding to mitigate related impacts, and solutions are available, but the measures will add to project costs and complexity. Quarterly in-period comments from companies covered by JPMorgan indicate that data-center demand remains strong and project timelines are broadly in line with expectations, although places such as Texas and Pennsylvania have already taken steps to address community concerns.

What does the report say about the pace of investment ahead?

  • JPMorgan expects AI investment to remain resilient after the midterm elections and potentially accelerate in 2027–2028: companies are advancing projects in response to growing demand and also want to act before political uncertainty rises ahead of the next presidential election.
  • Policy support varies by scenario: if Democrats win both the House and the Senate, the likelihood may increase of extending renewable-energy tax credits or even restoring some credits that have already been cut.